Main works due to commence next month (according to the County Council's website).
https://www.staffordshire.gov.uk/Hi...ternaccess/proposedstaffordwesternbypass.aspx
https://www.staffordshire.gov.uk/Hi...ternaccess/proposedstaffordwesternbypass.aspx
Project milestones include (times subject to change)
- On site activities begin: June 10 2019.
- Start piling works in Castletown: Early July 2019 (approximately seven months).
- Start piling works at Doxey Road car park: Early August 2019 (approximately seven months).
- Start piling works at Ten Pin and Lidl: Early October 2019 (approximately seven months).
- Roadworks at Doxey Road roundabout: Early September 2019.
- Roadworks between Doxey Road Bridge and Timberfields: Mid-October 2019.
- Demolition of old St Gobain buildings: Mid-October 2019.
- Roadworks at Rose Hill/Martin Drive roundabout: Mid-November 2019.
- Roadworks between Timberfields and Doxey Road roundabout: December 2019.
- Doxey Road car park viaduct beam installation: January 2020.
- Roadworks to Madford Retail Park: July 2020.
- River Sow bridge beam installation: Late July 2020.
- Works at Sainsbury car park north (subject to approval with Stafford Borough Council): Early December 2020.
- Works at Sainsbury Car Park South (subject to approval with Stafford Borough Coouncil): Early February 2021.
- Doxey Road railway bridge closure: Late March 2021.
- Scheme completion: August 2021.
- Works at Madford Retail Park (subject to approval with Aviva). Lidl Car Park late September 2020. Ten pin car park early October 2020. Curry’s/PC World car park early February 2021.